The manufacturing team has been working hard over the last few months, completing hundreds of prefabricated parts in order to commence the factory assembly of 55 large structural frames for the Clearwater Quays project in Christchurch.
Assembly of these frames starts next week and will continue throughout August and into September.
Early involvement in this project has enabled us to carefully plan the manufacturing process and prepare custom equipment to ensure a quality and consistent result.
All frames will be completed, checked and stored ahead of the build program to enable a rapid site assembly process.
This type of planning is only possible with early engagement and its been great to have a project team aware of the benefits of getting this process right.
Thanks to the project team for putting their trust in us, Logic Group NZ, Enovate Ltd, Pacific Environments NZ Ltd and Marty Verry from Red Stag Investments.
Source: TimberLab Solutions via LinkedIn
Latest Posts

Building a timber trampoline in the sky!

Mass timber solution to Canada’s housing crisis

Waikato Regional Theatre case study

Timber engineering of tomorrow

Go the Swiss!

EVE Music Hall — Croatia

Albert Park Pit Building

The Court Theatre – case study