Embodied Carbon Unicorn Moment

From the team at Logic Group:

Recently we were given the chance to truly test our V-Quest comparative analysis tool as a service.

The project, Five 5 storey apartment blocks, fully designed and ready to be consented. Designed in heavy weight concrete tilt panel, comflor and structural steel. This was a Wednesday and it was scheduled for consent application the following Monday. The developer heard of us and wanted to do a sanity check.

We took the existing design, ran it through V-Quest and provided an interactive comparative analysis of embodied carbon, cost and weight across 3 separate build methodology. Our tool analysed the existing heavy weight design and converted it to the expected mass timber (CLT & LVL) methodology and an optimised design Hybrid model (CLT Walls and floors, Structural Steel frame).

Within 48hrs we returned an analytical report that proved that the hybrid methodology was cost neutral, reduced the potential upfront embodied carbon by 750,000kg (3.75m total development kgs) and 800,000kg of weight per building. It gets better, the reduced weight proved to be key. With the weight savings the developer was able to replace his 16m deep piles with a 600mm gravel raft and add two floors to the height of the building.

Our reports don’t just return single sets of data, they provide comparative analysis of the potential options and examine how those data sets interact with each other. An embodied carbon calculation on its own provides limited information to make good decisions. When you know how that calculation interacts with cost and weight, well, now you can make confident decisions.

Talk to us, as sustainability is possible without breaking the bank. 

Latest Posts

Image
29 September 2026

Timber engineering of tomorrow

An airship hangar as a blueprint for the timber engineering of tomorrow: it is the gates that make the scale of this structure immediately comprehensible.  But the real highlight of...
Read More
Image
29 September 2026

Go the Swiss!

Bürogebäude Wood in Grenoble — The six-storey timber structure uses columns and beams spaced 4–6 m apart, supported on shallow concrete footings with tie-rods for seismic resistance; the eastern section...
Read More
Image
29 September 2026

EVE Music Hall — Croatia

This looks like an icon in the making – can’t wait to see the finished photos inside this magnificent space! The EVE Music Hall is set to become a new...
Read More
Image
29 September 2026

Albert Park Pit Building

Who doesn’t like civic buildings especially when they also serve as Grand Prix venues. Woods Bagot has been appointed to lead the architectural vision for the redevelopment of the Albert...
Read More
Image
22 September 2026

The Court Theatre – case study

The Court Theatre project is a purpose-built performing arts venue in Christchurch, designed to be the cultural heart of the city. The building integrates mass timber elements to enhance sustainability,...
Read More
Image
22 September 2026

Wood is Good Day at Te Hapara School

Hands-on Wood is Good Day gives students a glimpse into the people, technology and opportunities behind forestry. Te Hapara School students got up close to the world of forestry this...
Read More
Image
22 September 2026

Beyond the borders

When you look beyond our borders for where mass timber is gaining traction it’s often in education buildings. Maybe it’s because young people getting educated are a natural fit for...
Read More
Image
22 September 2026

Opening of Poutini Waiora

The opening of Poutini Waiora in Māwhera Greymouth celebrated a new facility designed to provide more comprehensive support for whānau and the wider West Coast community. The occasion also honoured...
Read More
Image
15 September 2026

Atlassian Central — the last panel is now in place!

The last timber panel is now in place at Atlassian Central, the final piece in a global milestone for the world’s tallest hybrid timber tower.  Also check out the great...
Read More